EYDE/PATHE : CONSTRUCTION OF MOTORWAY AND OTHER ACCOMPANYING WORKS IN THE SECTION : BEGINNING OF THE ROAD JUNCTION OF AGIA MARINA OF STYLIDA BEGINNING OF THE ROAD JUNCTION OF RACHES ON THE PATHE AXIS | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | HELLENIC MINISTRY FOR THE ENVIRONMENT, PHYSICAL PLANNING & PUBLIC WORKS/PATHE | |
Project Location | GREECE - PR. PTHIOTIDA | |
Construction Period | 2007 – 2010 | |
(%) Company Participation | 100 % | |
The project objective is the construction of the PATHE section from the Road Junction of Agia Marina to the Road Junction of Raches, which includes, the artery, of approximate length of 19.2 km, of typical cross-section of 22.65 m, of which 1.2 km is the widening or/and improvement of the tracing of the N.N.H. while the remaining 18.00 km are formed via a new tracing, tree double branch tunnels of total length of 3.00 km (for a single branch) with the two servicing buildings, four dale bridges (three of a double branch and one of a single branch) 1.8 km long in total (for a single branch), three underpass junctions, one bridge, upper and lower crosswalks and side and transverse roads 25 km long in total. τρείς ανισόπεδους κόμβους, μία γέφυρα, άνω και κάτω διαβάσεις και παράπλευρους και κάθετους οδούς συνολικού μήκους 25 χλμ. |
EYDE/PATHE : CONSTRUCTION OF MOTORWAY WORKS AND OTHER ACCOMPANYING WORKS IN THE SECTION : NEW WATERCOURSE OF SPERCHIOS END OF THE RODITSA MOTORWAY ON THE PATHE AXIS | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | HELLENIC MINISTRY FOR THE ENVIRONMENT, PHYSICAL PLANNING & PUBLIC WORKS/PATHE | |
Project Location | GREECE - PR. PTHIOTIDA | |
Construction Period | 2006 – 2009 | |
(%) Company Participation | 100 % | |
The project objective is the construction of the PATHE section from the New Watercourse of Sperchios to the end of the Roditsa Motorway, which includes, a) the artery, approximately 4.06 m long, as a widening or/and improvement if the tracing of the existing N.N.H., b) the underpass junction of Roditsa (of the trumpet type), which serves as a connection of the city of Lamia with the PATHE motorway, c) the side and transverse roads and local roads, d) the rearrangement of the New Watercourse of Sperchios, from its deboutchment to K.P. 5+561 (approximately 250 m uphill to PATHE), The K.P. which is identified with K.P. 5+600 of the hydraulic design, e) the rearrangement of the Lamia ditch from its extrusion in the New Watercourse of Sperchios (K.P. 0+000) to K.P. 5+000, f) The rearrangement of the Xirias torrent section, approximately 660 m long and g) the restoration of the affected works of the irrigation networks Anthili Roditsa. |
EGNATIA ODOS : SECTION PANAGIA GREVENA, FROM K.P. 6+300 TO K.P. 16+300 (4.1.1.s 4.1.2.s) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | GREECE - PR.GREVENON | |
Construction Period | 2005 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the construction of the Egnatia Road (E.R.) section from Panagia to Grevena in the county of Grevena, 10 km long. This section includes the opening up of the motorway with a typical cross-section of 10.50 m per branch which includes five twin tunnels with maximum length of 785 m and with total length of 5.9 km (for a single branch) and two double bridges 1.7 km long (for a single branch) and with maximum opening of 120 m. |
EGNATIA : SECTION PANAGIA GREVENA, FROM THE PANAGIA ROAD JUNCTION TO K.P. 6+300 (4.1.1.S) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | GREECE - PR.IOANNINON - PR.GREVENON | |
Construction Period | 2005 – 2008 | |
(%) Company Participation | 100 % | |
This section includes the opening up for the motorway with a typical cross-section of 10.50 m per branch which includes two twin tunnels correspondingly 2.7 km and 1.7 km long and of a total length of 8.4 km (for a single branch), a double bridge 350 m long (700 for a single branch) and with a maximum opening of 160 m, with cantilever structure, as well as the completion of the underpass junction of Panagia which includes an artery 1.3 km long, three branches, a double bridge 200 m long (600 m for a single branch) and two branch bridges. |
EYDE/PATHE : CONSTRUCTION OF MOTORWAY WORKS AND OTHER ACCOMPANYING WORKS SECTION SKARFIA (OSE BRIDGE) BEGINNING OF THE THERMOPYLES MOTORWAY ON THE PATHE AXIS | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | HELLENIC MINISTRY FOR THE ENVIRONMENT, PHYSICAL PLANNING & PUBLIC WORKS/PATHE | |
Project Location | GREECE - PR. FTHIOTIDA | |
Construction Period | 2006 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the construction of a PATHE section of an approximate total length of 17.400 km. This project includes the construction of the motorway in the section of Skarfia Thermopyles approximately 17.400 km long, the construction of two semi-underpasses (S-U of Skarfia and S-U of Thermopyles) and of one underpass junction (Motorway of Molos) and the restoration of the transverse and side local roads network as well as the creation of side roads wherever required. Also full construction of the road is anticipated i.e. earthmoving, road layering, bitumen works, technical works (large and small), draining straining, signaling safety measures, junction, underpass and parking flats electric power supply and lighting, telephone supply infrastructure, irrigation and seeding works and environmental protection works |
HOSPITAL OF CORFU ; NEW CONTRACT WORK FOR THE COMPLETION OF CONSTRUCTION OF BUILDING ELECTRICAL AND MECHANICAL WORKS FOR THE G.H. OF CORFU | ||
![]() |
Project Category | BUILDINGS
|
Project Owner | DEPANOM | |
Project Location | GREECE - PR. CORFU | |
Construction Period | 2007 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the construction of building electrical and mechanical works for the completion of the project, changes modifications of building and electrical and mechanical works for the re-composition of certain areas into Hospital sections and the creation of new areas, changes modifications of electrical and mechanical installations, i.e. electrical and mechanical installations for upgrading, improving and supplementing the electrical and mechanical installations and finally the works to the limits of the hospital area for installation connections with the networks of DEH, OTE, water supply and for the disposal of wastes to the nearest approved recipient. |
HOSPITAL OF KATERINH : NEW CONTRACT WORK FOR THE COMPLETION OF THE CONSTRUCTION OF BUILDING ELECTRICAL AND MECHANICAL WORKS FOR THE G.H. OF KATERINI | ||
![]() |
Project Category | BUILDINGS
|
Project Owner | DEPANOM | |
Project Location | GREECE - PR. PIERIA | |
Construction Period | 2007 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the construction of building electrical and mechanical works for the completion of the project, changes modifications of building and electrical and mechanical works for the re-composition of certain areas into Hospital sections and the creation of new areas, changes modifications of electrical and mechanical installations, i.e. electrical and mechanical installations for upgrading, improving and supplementing the electrical and mechanical installations and finally the works to the limits of the hospital area for installation connections with the networks of PPC, OTE, water supply and for the disposal of wastes to the nearest approved recipient. |
EGNATIA ODOS : DERVENI - SERRES - PROMACHONAS : ROAD JUNCTION OF LEFKONA - ROAD JUNCTION OF CHRISTOS (60.2.2) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | GREECE - PR. SERRON | |
Construction Period | 2006 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the construction of the section Strymoniko Road Junction of Lefkona Road Junction of Christos of the Egnatia Roadtransverse link Thessaloniki Serres Promachonas, of a total length of 22 km. This section includes the opening up of the motorway with a quadruple footprint which include the Strymonas river bridge and other bridges of a total length of 1.8 km (for a single branch) and with a maximum opening of 44.7 m, lower crosswalks, three underpass junctions of Strymoniko with total length of branches of 1.34 km, of Lefkona with total length of branches of 1.73 km, as well as side and transverse roads of a total length of 25 km |
URGENT FLOOD PREVENTING WORKS FOR THE PROTECTION OF ATTICA REGIONS WHICH ARE | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | HELLENIC MINISTRY FOR THE ENVIRONMENT, PHYSICAL PLANNING & PUBLIC WORKS/PATHE | |
Project Location | GREECE - PR. ATTIKI | |
Construction Period | 2007 – 2008 | |
(%) Company Participation | 100 % | |
The project objective is the faster possible improvement of the flood-stricken outflow regions via interventions improvements and additions to be carried out in the streams of Sarantapotamos, Eschatia, Agia Triada and Acharnon in selected sections needing immediate intervention, so that possible floods that may emanate from the fires on Parnitha during July 2007, may be met in the best possible way |
EGNATIA ODOS : SECTIONS A) FROM THE ROAD JUNCTION OF CHRYSOUPOLI TO THE INTERSECTION WITH THE NATIONAL HIGHWAY WEST OF THE NESTOS RIVER AND OF THE NESTOS BRIDGE B) FROM THE EASTERN MOUTH OF THE NESTOS TUNNEL TO THE ROAD JUNCTION OF VALIANOS (14.1.2 14.2 | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | GREECE - PR.KAVALAS | |
Construction Period | 2005 – 2007 | |
(%) Company Participation | 100 % | |
The project objective is the construction of the Egnatia Road (E.R.) sections from the road junction of Chrysoupoli to the National Highway of Kavala Alexandroupoli and from the western mouth of the Nestos tunnel to the motorway of Valianos, of a total length of 15.23 km. This section includes the opening up of the motorway with total width of 24.5 m which includes a twin tunnel 310 m long, a vehicle - machinery housing building, upper lower crosswalks as well as side and transverse roads of a total length of 25 km |
COMPLETION WORKS OF SECTION FROM JUNCTION IGOUMENITSA'S UP TO JUNCTION SELLON | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | Greece - Igoumenitsa (from junction Igoumenitsa's up to junction Sellon) | |
Construction Period | 1999 – 2005 | |
(%) Company Participation | 30 % | |
Construction of additional works with companion craftworks, sewerage, completion of water supply works, electricity, marking - security additional works, completion lateral roads, etc. |
ELEFSINA - STAVROS - SPATA A/P MOTORWAY & IMITOS WESTERN PERIPHERAL MOTORWAY | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Attica | |
Construction Period | 1996 – 2004 | |
(%) Company Participation | 8,5856 % | |
A project of vital importance for Attica and Greece which comprises the Design, Construction & Operation of Elefsina - Stavros - Spata A/P Motorway and Imitos Western Peripheral Motorway. Designed according to the most up-to-date specifications as a closed motorway with tolls, which will form the internal peripheral ring road of the wider metropolitical area of the capital city. It consists of two main motorways: ESSM with a length of 50,4 km and IWPM with a length of 12,9 km.
|
CONSTRUCTION OF SAILING OLYMPIC CENTER OF St. KOSMAS - B΄ PHASE | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works/ ΟΕ 2004 | |
Project Location | Greece - Attica, St. Kosmas | |
Construction Period | 2002 – 2004 | |
(%) Company Participation | 60 % | |
Marin and land construction of the Sailing Olympic Center in St. Kosmas, for carrying out the pre-Olympig games on August of 2003 and the Olympig games of 2004. |
OLYMPIC VILLAGE CONSTRUCTION AND POST GAMES ADJUSTMENTS - SECTION C 602 RESIDENTIAL UNITS AND INFRASTRUCTURE | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | OLYMPIC VILLAGE 2004 S.A. | |
Project Location | Greece - Lekanes, Aharnes, Attica | |
Construction Period | 2001 – 2003 | |
(%) Company Participation | 33,33 % | |
CONSTRUCTION OF 602 RESIDENTIAL UNITS (96 BUILDINGS) AT THE OLYMPIC VILLAGE , IN LEKANES AREA (AHARNES), CONFIGURATION OF SURROUNDING AREA, ROADS AND INFRASTRUCTURE. |
EGNATIA ROAD: POLYMYLOS - LEFKOPETRA SECTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | Greece - Prefecture of Imathia - Prefecture of Kozani | |
Construction Period | 1999 – 2003 | |
(%) Company Participation | 8,99 % | |
Project consists of the construction of Polymylos-Lefkopetra section of the Egnatia Highway at the prefectures of Kozani and Imathia, with a total length of 12,9 km. This section includes: a. Highway opening up at the Polymylos-Lefkopetra section (5,1), with a total length of 12,9 km and a typical cross-section of 22,00 m. b. Restoration of the lateral and side road network at the area of Polymylos (Crossing 33). c. Restoration of existing installations of public utility undertakings. d. Construction of bilateral parking opening at km 24+000. Full road construction is provisioned, that is: earthworks, road pavement, asphalt works, (minor and major) technical works, tunnels, sewage, drainage, signage, telephone line, tunnel fire protection, lighting of tunnels and major technical works, hydroseeding. |
NEW ATHENS INTERNATIONAL AIRPORT FUEL PIPELINE | ||
![]() |
Project Category | INDUSTRIAL & ELECTROMECHANICAL WORKS
|
Project Owner | ATHENS AIRPORT FUEL PIPELINE COMPANY | |
Project Location | Greece - Attica Prefecture (Aspropyrgos - Spata ) | |
Construction Period | 2000 – 2003 | |
(%) Company Participation | 8,59 % | |
Construction of a 51.330 m fuel pipeline, which will start from Hellenic Petroleum refineries and will end up at the delivery station of the new International Airport in Spata, "Eleftherios Venizelos". |
CONSTRUCTION OF SUPPLEMENTARY WORKS OF PATRAS-ATHENS-THESALONIKI-EVZONI (PATHE) MOTORWAY IN THE YLIKI-AG. KONSTANTINOS SECTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | PUBLIC WORKS SERVICE FOR PATHE MOTORWAY (EYDE/PATHE) | |
Project Location | Greece - Prefecture of Fthiotida | |
Construction Period | 2000 – 2002 | |
(%) Company Participation | 100 % | |
Project involves full road construction works, i.e. earthworks, technical works, road pavement, asphalt works, signage, protection equipment, full fencing and electric lighting, according to the provisions of the approved designs, SOS telephone line infrastructure, irrigation and fire fighting infrastructure, storm drainage infrastructure, as well as any additional piping along the roads for installation of cables, which will be done only upon request and according to the guidelines of the department. |
LAMIA'S GENERAL HOSPITAL. NEW BUILDING GROUP FOR 300 BEDS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Lamia, Fthiotida's perfecture | |
Construction Period | 1997 – 2002 | |
(%) Company Participation | 100 % | |
Construction of new building group 300 beds, total building surface 40.185,79m2. The constructing works are : a) building, such as excavations, concrete works, walls, wood works, metal works and cover works, b) Elektromechanical installations, such as water supply, sewerange, elektrical, air conditioning, fire extinction, lightning rod, steam installation, medical gas - gas, c) surrounding works, such as roads, perking, supporting walls, ramps, pavements etc. |
INFLAMMABLE LIQUID PIPELINE EXPANSION FROM STRIMONA'S STORAGE PLACE UP TO KAVALA | ||
![]() |
Project Categories | INDUSTRIAL & ELECTROMECHANICAL WORKS
|
Project Owner | General Army Staff / Military Aviation Authority | |
Project Location | Greece - Eleftheroupoli's area, Kavala's perfecture | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 99 % | |
61 Km pipeline construction from API 5 L GRADE B, two extraordinary points receiving , internal scalper trap station, pipeline descending safety , and underground pipelines with electricity supply stations, filling and modification of the existing junctions of high and low pressure, filter stations as well as other mechanical works required for the correct pipeline operation. |
EXTENSION OF LINE 2: SEPOLIA - THIVON TUNNEL | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | ATTIKO METRO SA | |
Project Location | Greece - Athens | |
Construction Period | 2000 – 2002 | |
(%) Company Participation | 33,33 % | |
Project includes pile works, C&C tunnel excavation and tunnel excavation using the NATM method. Furthermore, it includes the pile and construction works of departure shaft using the C&C method, OFS departure section which will be constructed using NATM method, transportation and mounting of the OFS equipment and the construction works of the tunnel with OFS. |
EGNATIA HIGHWAY: SECTION N. KARVALI - A.K. HRYSOUPOLIS (14.1.1) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | Greece - N. KARVALI - A.K. HRYSOYPOLIS | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 4 % | |
Construction of Egnatia Highway from km 15+600 to km 16+350, from km 0+000 to km 4+200, from km 8+200 to km 8+400 and from km 9+520 to km 10+700 and of the parallel motorway.
|
ATTICA ROAD. IMITOS WESTERN PERIPHERAL MOTORWAY (IWPM) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Attica | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 38 % | |
1) Κατασκευή αυτοκινητοδρόμου συνολικού μήκους 6,5χλμ + 2 χλμ διαπλάτυνση της οδού Κατεχάκη τριών λωρίδων + ΛΕΑ ανά κατεύθυνση.
2) Κατασκευή Σηράγγων Κολεγίου, Κόμβου Δημοκρίτου και Δημοκρίτου συνολικού μήκους 1.749 μ. 3)Κατασκευή CUT & COVER 18 συνολικού μήκους : 3.180 μ. |
THIRD ROAD REHABILLITATION CN2 (E85) GH. DOJA-FITIPESTI K.P. 263+000 TO 302+000 | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | National Administration of RoadsMinistry of Transport – Romania | |
Project Location | Romania - BACAU | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 50 % | |
Reconstruction and restoration of the GH. DOJA-FITIPESTI K.P. highway 263+000 TO 302+000. |
CONSTRUCTION OF SUPPLEMENTARY WORKS OF PATRAS-ATHENS-THESALONIKI-EVZONI (PATHE) MOTORWAY IN THE SKOTINA-KATERINI SECTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | PUBLIC WORKS SERVICE FOR PATHE MOTORWAY (EYDE/PATHE) | |
Project Location | Greece - Prefecture of Pieria | |
Construction Period | 2000 – 2002 | |
(%) Company Participation | 90 % | |
Project involves full road construction works, i.e. earthworks, technical works, road pavement, asphalt works, signage, protection equipment, full fencing and electric lighting, according to the provisions of the approved designs, SOS telephone line infrastructure, irrigation and fire fighting infrastructure, storm drainage infrastructure, as well as any additional piping along the roads for installation of cables, which will be done only upon request and according to the guidelines of the department. |
CONSTRUCTION OF CARS PROTECTED BUILDING AT THE REGION OF LARISSA | ||
![]() |
Project Categories | BUILDINGS
Administration & Office Buildings |
Project Owner | HELLENIC AIR FORCE / PROJECT OFFICE OF AIR FORCE | |
Project Location | Greece - Prefecture of Larissa | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 23,5 % | |
Design and construction including construction of tunnels and specialised electromechanical works, according to strict specifications, as well as configuration of the surrounding area. |
SETTLEMENT AND DIVERSION OF SPERHIOS RIVER DOWNSTREAM OF NEW HIGHWAY AND LAMIAS TRENCH FROM KM 0+000 UP TO KM 7+009 | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works - SOLID GREECE AREA | |
Project Location | Greece - Sperhios river, Lamia's area, Fthiotida Perfecture | |
Construction Period | 1998 – 2002 | |
(%) Company Participation | 100 % | |
Settlement and widening of the new channel diversion of Sperhios river from Km 0+000 (intersection with a new channel) up to Km 7+009. |
MAIN WATER SUPPLY CANAL D1. SECTION POURNARI II - IMARET | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works - RECLAMATION CONTACTS COURSE (D7) | |
Project Location | Greece - Arta's perfecture, Ipiro's region, section Pournari - Imaret | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 25 % | |
Construction of main water supply canal trench D1, with total length nearly 4.063m, to whivh the begining is at project of Hydro-Electerical Station of Pournari II and the conclusion near 400m downstream Imaret's project. The whole project includes the concrete rectangle canal, width b=4,00m and high changeable high walls, all the craftworks of it and also the hydro-mechanical equipment supply and installation (e.x. s flowfence for adjustment of downstream level, water supply regulators etc ). |
SECTION KEFALOVRISO - AGELOKASTRO. AGRINIO'S DEVIATION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Kefalovriso - Agelokastro. Etoloakarnania's perfecture | |
Construction Period | 1997 – 2002 | |
(%) Company Participation | 0,5 % | |
Total construction of road section from Km 0+520 up to Km 13+500 as well as the construction of Halikio and Agelokastro over-pass junctions. Also the connection of the above road section with the existing national road No5 to so as to operate as continuation of the national road No5. |
CONSTRUCTION & ELECTROMECHANICAL WORKS FOR THE RESTORATION OF THE CAPODISTRIAN ORPHANAGE IN AIGINA AND ITS TRANSFORMATION INTO A DIACHRONIC MUSEUM | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | MINISTRY OF CULTURE | |
Project Location | Greece - Aigina | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 100 % | |
Total reconstruction and restoration of a 170-year old building into its initial form through special works of static reinforcement (groutings, shotcrete, piles), usage of materials compatible with those initially used (puzzolana, hydraulic lime). Total restoration of the morphological elements of the facets. Electromechanical works. |
ΤΑΜΙΕΥΤΗΡΑΣ ΚΑΡΛΑΣ & ΣΥΝΑΦΗ ΕΡΓΑ | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefecture of Magnesia | |
Construction Period | 1999 – 2002 | |
(%) Company Participation | 87,45 % | |
A water reservoir will be established at the lowest south-eastern part of Karla Lake and cover an area of 42.000.000 sq.m. It will be formed through the construction of two embankments, eastern and western, with a total length of about 13 km. There is also a provision for the construction of water-tightening embankments with a total length of 7.200 m along parts of the northern bank of the water reservoir. In the water reservoir, S3, S4, S6 and S7 collectors will flow as well as streams of the small mountain basins ending up directly into the reservoir. |
SECTION 1.14: IGOUMENITSA-PEDINI, MESOVOUNIO-GRIKAS TUNNELS | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | Greece - Prefecture of Thesprotia | |
Construction Period | 1999 – 2001 | |
(%) Company Participation | 100 % | |
Project covering a length of 2.035 m, includes construction of the following works: 1. Full construction of the twin tunnels S2 in Mesovounio (435,460 m) and S3 in Grika-Dikorfo (680,640 m) including road pavement, asphalt works and electromechanical installations. 2. Full construction of sections of the road, i.e. road section between the tunnels (approx. 500 m long) and sections at the beginning and at the end of the project (approx. 200 m long each). 3. Construction of electric lighting and signs of the road in a length of 200 m before and after tunnels as well as in the in-between section of the road. |
NEW CARGO FACILITIES OF OLYMPIC AIRWAYS AT THE NEW ATHENS INTERNATIONAL AIRPORT, | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | OLYMPIC AIRWAYS | |
Project Location | Greece - Athens | |
Construction Period | 2000 – 2001 | |
(%) Company Participation | 33,33 % | |
Contract refers to the design and construction of the new Olympic Airways cargo facilities at the new Athens international airport "Eleftherios Venizelos", with a total area of 21.000 sq.m.. |
CONSTRUCTION OF TUNNELS, EARTHWORKS AND OTHER TECHNICAL WORKS FOR THE NEW DOUBLE ATHENS - THESSALONIKI RAILWAY LINE BETWEEN KM 399+300 AND KM 411+300 (PLATAMONAS-LEPTOKARYA) AND RESTORATION WORKS FOR THE PARALLEL HIGHWAY - SECTION 2A | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | ERGOSE SA | |
Project Location | Greece - Perfecture of Pieria - Platamonas - Leptokarya | |
Construction Period | 1996 – 2001 | |
(%) Company Participation | 98 % | |
Construction of a section of the double Athens-Thessaloniki railway line in the area of Platamonas-Leptokarya and of the parallel highway. The tunnel's entrance and exit are constructed with Cut & Cover. Indicative references of works: Railway Line Length= 11,354 m., Tunnel Length=4.222 m., Highway Length =14.560 m, Major Technical Works = 13. |
Construction, completion and maintenance of 411 houses and public building and main servises in Area No3 of the Sulaibikhat East | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | HOUSING AUTHORITY | |
Project Location | Kuwait – | |
Construction Period | 1998 – 2001 | |
(%) Company Participation | 100 % | |
Construction, completion and maintenance of 411 houses, public building and main servises in Area No3 of the Sulaibikhat East. |
1st Multisectoral High School (EPL) of ACHARNAI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | SCHOOL BUILDING ORGANIZATION | |
Project Location | Greece - Acharnai, Attica | |
Construction Period | 1999 – 2001 | |
(%) Company Participation | 100 % | |
Construction works, Electromechanical installations and schoolyard. Full completion. |
NEW DOUBLE RAILWAY LINE FROM ELEFSINA TO KORINTHOS ( TUNNEL CONSTRUCTION, EARTH WORKS AND OTHER CRAFTWORKS) EFTAXIA TO NEW PERAMOS AREA | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | ERGOSE S.A. | |
Project Location | Greece - ATTIKI'S PERFECTURE EFTAXIA AREA - NEW PERAMOS JUNCTION | |
Construction Period | 1996 – 2001 | |
(%) Company Participation | 0,22 % | |
Construction of foundation for the new double normal width and high speed railway line from Elefsina to Korinthos at section area Eftaxia - George River-bed, longtitude 6,2 Km. Typical works reference: 1.625m Tunnel. Final opening : 11,00m. Highway (New Highway Athens - Korinthos) overpass craftwork length 75,00m (opening 11,00m). Railway overpass craftwork (opening 10,50m), small craftworks, sewers and supporting walls, escape tunnel length 400m, highway supporting wall built with piles length 72m, tunnel cut & cover length 32m, lateral roads with companion works. |
BUILDINGS OF THE MEDICINE DEPARTMENT (PHASE A) | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | DEMOKRITOS UNIVERSITY OF THRACE | |
Project Location | Greece - ALEXANDROUPOLI (Dragana, N. Hili) | |
Construction Period | 1998 – 2001 | |
(%) Company Participation | 100 % | |
Construction and Electromechanical works at the University campus of Alexandroupoli. Buildings 6,7, and 12. Configuration of surrounding area. |
ALEXANDROUPOLI GENERAL REGIONAL HOSPITAL | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | DEPANOM | |
Project Location | Greece - Alexandroupoli, Evros | |
Construction Period | 1995 – 2001 | |
(%) Company Participation | 19,5 % | |
Design and Construction of Building and Electromechanical Works and Supply - Installation of basic medical equipment . |
DAM CONSTRUCTION AT SYKIA, ARTA, GREECE | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefecture of Arta - Area of Sykia | |
Construction Period | 1996 – 2001 | |
(%) Company Participation | 40 % | |
Dam construction including all necessary works for excavation, foundation, construction with impervious stratum, filters, fixing materials, protection rip-rap, etc, water diversion and control, construction of protection works (spillway, drainage tunnel, etc), concrete injections, tunnels of concrete injections and access tunnels. |
EXPLOITATION OF A 24.000 Μ2 FIELD IN ATHENS - ERECTION OF ERRIKOS DYNAN HOSPITAL | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | BACON SA | |
Project Location | Greece - Attica | |
Construction Period | 1994 – 2000 | |
(%) Company Participation | 25 % | |
Self-financed construction project. It includes Design-Construction and delivery with the system of exchange of Hospital (Errikos Dynan) without medical equipment and of complex of office and shop buildings (Politia Center) in return to the exchange. Indicative project description: Hospital: Total area of 50.183 m2, with 2 basements, ground floor & 7 floors, with 420 beds, seminar rooms, theater, restaurants, cafeteria, outpatient department, storage rooms, 81 parking places. Politia Center Commercial Center: Total area of 70.000 m2, with 3 basements, ground floor & 7 floors, in 4 separate buildings and 900 parking places. |
Construction, completion and maintenance of 121 houses and public building and main servises in Area No1 of the East Sulaibikhat East | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | HOUSING AUTHORITY | |
Project Location | Kuwait – | |
Construction Period | 1997 – 2000 | |
(%) Company Participation | 100 % | |
Construction, completion and maintenance of 411 houses, public building and main servises in Area No3 of the Sulaibikhat East. |
Construction, completion and maintenance of 203 houses and public building and main servises in Area No2 Part I of the West Sector of Umm Al - Haiman Housing Project | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | HOUSING AUTHORITY | |
Project Location | Kuwait - | |
Construction Period | 1997 – 2000 | |
(%) Company Participation | 100 % | |
Construction, completion and maintenance of 411 houses, public building and main servises in Area No3 of the Sulaibikhat East. |
CONSTRUCTION OF GOTSE DELCHEV – DRAMA APPROACH TO BORDER CROSSING | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | MINISTRY OF REGIONAL DEVEPO | |
Project Location | MINISTRY OF REGIONAL DEVEPO | |
Construction Period | 2000 – 2000 | |
(%) Company Participation | 1 % | |
Construction 07 Gotse – Delcher Drama Approachroad to Border Crossing Rehabillitation Strengthening and Improvement 07 road E-79 Dupnitsa Kulata. |
CONSTRUCTION OF IGOUMENITSA COURT HOUSE PHASE A + C | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | THEMIS KATASKEVASTIKI SA | |
Project Location | Greece - Igoumenitsa, Prefecture of Thesprotia | |
Construction Period | 1998 – 2000 | |
(%) Company Participation | 100 % | |
Earthworks and construction of the supporting structure of the new Igoumenitsa Court House with reinforced concrete. |
EGNATIA HIGHWAY: IGOUMENITSA - PEDINI; CONSTRUCTION OF THE KOUMARIA - AG. ANASTASIA SECTION KM 14+500 TO KM 19+500 | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | EGNATIA ODOS S.A. | |
Project Location | Greece - Perfecture of Ioannina: Koumaria - Ag. Anastasia | |
Construction Period | 1995 – 1999 | |
(%) Company Participation | 70 % | |
Construction of a section of Egnatia highway with a total length of 5 km with two traffic lanes and hard shoulder per direction and an island with New Jersey - type guard rails. It includes construction of two tunnels with total length of 1.200 m (2 x 400 + 2 x 200). Tunnels' entrances and exits, having a total length of 700 m, are constructed with the Cut & Cover method. |
ERECTION OF MULTI-STOREY BUILDING FOR THE MACEDONIA THRACE BANK AT VOLOS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | MACEDONIA THRACE BANK | |
Project Location | Greece - Volos | |
Construction Period | 1992 – 1999 | |
(%) Company Participation | 90 % | |
Self-financed building project, which includes the erection of the multi-storey building of the central offices of Macedonia - Thrace bank. |
ILIKI - AG. KONSTANTINOS HIGHWAY ATALANTI - ARKITSA SECTION (FROM KM 141+010 TO KM 149+020) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works / Patra-Athesns-Thesaloniki-Evzoni (PATHE) highway | |
Project Location | Greece - Prefecture of Fthiotida - Area between Atalanti a | |
Construction Period | 1994 – 1999 | |
(%) Company Participation | 5 % | |
Full highway construction (widening) with a total length of 8,1 km (from km 141+010 to km 149+020) with all related works, i.e. earthworks, technical works, road pavement, asphalt works, signage, protection, sewage and drainage works, irrigation, lighting, telephone line, etc. |
ILIKI - AG. KONSTANTINOS HIGHWAY ILIKI - KASTRO SECTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works / Patra-Athesns-Thesaloniki-Evzoni (PATHE) highway | |
Project Location | Greece - Prefecture of Fthiotida - Area between Iliki and Kastro - Greece | |
Construction Period | 1995 – 1999 | |
(%) Company Participation | 74 % | |
Full highway construction with a total length of 18,4 km (from km 90+600 to km 109+000) with all related works, i.e. earthworks, technical works, road pavement, asphalt works, signage, protection, sewage and drainage works, irrigation, lighting, telephone line, etc. |
SKOTINA - KATERINI HIGHWAY. FULL CONSTRUCTION WORKS OF THE HIGHWAY AND RELATED WORKS AT THE LITOCHORO - DIO SECTION FROM KM 9+500 TO 19+000 | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works / Patra-Athesns-Thesaloniki-Evzoni (PATHE) highway | |
Project Location | Greece - Prefecture of Pieria - Litochoro - Dio | |
Construction Period | 1995 – 1999 | |
(%) Company Participation | 87 % | |
Modification of the highway at the Litochoro - Dio section of the national road with full construction of parallel roads and construction of Litochoro interchange and four vertical roads. It consists part of the "Skotina - Katerini" project and extends from km 9+500 to 19+000 with the starting point of the kilometer marking being at the area of Skotina. |
FULL HIGHWAY CONSTRUCTION AND ALL RELATED WORKS AT LARISSA BY - PASS (EASTERN) FROM km 346+000 to 368+000 - 3rd SECTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works / Patra-Athesns-Thesaloniki-Evzoni (PATHE) highway | |
Project Location | Greece - Larissa | |
Construction Period | 1995 – 1999 | |
(%) Company Participation | 50 % | |
Construction with new road-surveying of Larissa Eastern by-pass which will be part of the new, under construction Athens-Thessaloniki highway, with related works (adjacent roads, trancent roads, link roads with any interchanges required etc.). The total length of the new artery is 22 km while the length of the adjacent roads is 44 km. |
STUDY AND CONSTRUCTION OF BIOLOGICAL REFINING INSTALATIONS AT INOFITA AREA OF SHIMATARI | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Association for biological refining of Inofita area of Shimatari | |
Project Location | Greece - Inofita, Viotias Perfecture | |
Construction Period | 1993 – 1999 | |
(%) Company Participation | 50 % | |
Construction of biological refining Installations including waste pre-elaboration, supply measure, manholes and dividors, landslip and ventilation tanks, pump-houses for mud and foam recirculate and turning down etc. |
CONSTRUCTION OF HIGHWAY SECTIONS IGOUMENITSA - PEDINI | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - St. Nikolaos - Koumaria | |
Construction Period | 1995 – 1999 | |
(%) Company Participation | 31,5 % | |
Construction of highway with the companion craftworks ( earthworks, small and big craftworks, tunnel construction that are foreseed at the meditation. |
CONSTRUCTION OF MARINE WORKS AT THE CENTRAL PORT OF PIRAEUS - PHASE A' | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Piraeus Port Authorities SA | |
Project Location | Greece - Piraeus | |
Construction Period | 1996 – 1999 | |
(%) Company Participation | 5 % | |
Construction of Marine Works at the Central Port of Piraeus - Α+B51' Contract phase. |
PPC NETWORKS IN THE PREFECTURE OF LARISSA, Κ2, CONTRACT NUMBER 2164134 | ||
![]() |
Project Category | INDUSTRIAL & ELECTROMECHANICAL WORKS
|
Project Owner | Public Power Corporation | |
Project Location | Greece - Larissa | |
Construction Period | 1996 – 1999 | |
(%) Company Participation | 1,13 % | |
Construction of PPC network works, such as aerial and subterranean medium and low power lines, aerial distribution sub-stations, subterranean transmission lines and their connections to the network, settlements and various auxiliary works. |
CONSTRUCTION OF EFPIRIDON AQUEDUCT | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Athens Water Supply and Sewerage Company (EYDAP) | |
Project Location | Greece - Attica | |
Construction Period | 1996 – 1999 | |
(%) Company Participation | 49 % | |
Construction of an aqueduct with all necessary works, i.e. earthworks, shoring, open and closed concrete pipes.
|
SETTLEMENT, DEEPENING AND SUPPLEMENTARY, TECHNICAL WORKS OF MIDLE AND DOWN FLOW OF VIOTIKOS KIFISSOS | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Viotikos Kifissos, Viotias prefecture | |
Construction Period | 1994 – 1998 | |
(%) Company Participation | 100 % | |
Total intervention at Viotikos Kifissos, at the midle flow from flowfence BOOT up to KM 13+600 also at the down flow from flowfence BOOT up to the concentrated canal. Specialy, works takes place at craftwork possitions, so that the concrete works be done under dry conditions, constructions for the safety of excavation sloping and widening of cutting of Viotikos Kifissos, drainpipes construction, dethronement of old stone coating and stonebuilt, steps construction, craftworks, etc. |
ILIKI - ST. KONSTANTINOS. SECTION KASTRO - MARTINO | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Υ.ΠΕ.ΧΩ.Δ.Ε / ΠΑΘΕ – ΤΜΗΜΑ ΘΗΒΑΣ | |
Project Location | Greece - Kastro - Martino Viotia's Perfecture | |
Construction Period | 1995 – 1998 | |
(%) Company Participation | 30 % | |
Construction of highway with companion works (Martino's overpass Junction, lateral roads, cross roads with any overpass intersections, sewerage and drainage works, marking - securement etc. |
CONSTRUCTION AND OPERATION OF MOTORISTS SERVICE STATION FOR ATHENS - LAMIA HIGHWAY AT KM 43+000 | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | ΑΤΕΜΚΕ S.A | |
Project Location | Greece - KM 43+000 ATHENS - LAMIA HIGHWAY | |
Construction Period | 1993 – 1997 | |
(%) Company Participation | 100 % | |
Construction of two-side motorists service stations at the sublimity of km 43+000 of Athens - Lamia highway ay Malakasa area. |
PEPSICO HBH - NEW FACTORY IN OINOFYTA - BOIOTIA, CONSTRUCTION WORKS (PHASE 4) | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | PEPSICO HBH | |
Project Location | Greece - Inofita, Viotias Perfecture | |
Construction Period | 1997 – 1997 | |
(%) Company Participation | 100 % | |
Construction of industrial floors, buildings, wells, lofts, biological waste treatment. |
HERACLES | ||
![]() |
Project Category | ΠΑΡΟΧΗ ΥΠΗΡΕΣΙΩΝ
|
Project Owner | HERACLES | |
Project Location | Greece - Olympos mine, Platanos mine, Magnesia | |
Construction Period | 1991 – 1996 | |
(%) Company Participation | 100 % | |
Mining, loading and feeding of calcareous rock from OLYMPOS & PLATANOS mines of HERACLES, at the prefecture of Magnesia, into the corresponding stone mills.
|
DESIGN AND CONSTRUCTION OF 63 TYPE A GROUND-FLOOR RESIDENCES AND 31 TYPE B GROUND-FLOOR RESIDENCES IN VILLAGES OF GREVENA PREFECTURE USING THE CONVENTIONAL WAY OF CONSTRUCTION | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefecture of Grevena | |
Construction Period | 1995 – 1996 | |
(%) Company Participation | 100 % | |
Design and construction of 63 residences of 50 m2 each and 31 residences of 60 m2 each in villages of Grevena Prefecture. |
RESEARCH INSTITUTE OF THESSALONIKI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry of Industry Research and Tecnology | |
Project Location | Greece - Thessaloniki | |
Construction Period | 1996 – 1996 | |
(%) Company Participation | 33,33 % | |
Building of chemical processes research laboratories and incubators for similar enterprises. |
DESIGN AND CONSTRUCTION OF 68 TYPE B GROUND-FLOOR RESIDENCES IN VILLAGES OF GREVENA PREFECTURE USING THE SYSTEM OF HEAVY PREFABRICATION | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefecture of Grevena | |
Construction Period | 1995 – 1996 | |
(%) Company Participation | 25 % | |
Group of type B residences which includes independent ground-floor exalted residences. |
URGENT WORKS FOR THE REMOVAL OF EARTH DISPLACEMENT AT THE SECTION MARKOPOULOU JUNCTION - OINOFYTA JUNCTION FROM KM 18+650 TO KM 18+850 ON THE ATHENS - LAMIA HIGHWAY | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Oinofyta | |
Construction Period | 1994 – 1996 | |
(%) Company Participation | 100 % | |
Full construction of works for removal of earth dispacement (earthworks, technical works, drainage works, etc). |
CONSTRUCTION OF CLOSED GYMNASIUM AT PATRA BOZAΪTIKA'S AREA | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | GENERAL SECRETARIAT OF ATHLETICS | |
Project Location | Greece - Patra | |
Construction Period | 1990 – 1995 | |
(%) Company Participation | 100 % | |
Construction of closed gymnasium with room areas at four (4) levels ( underground and three floors). Forecasting for 4.150 audienc sheets. The covering of gumnasium is with metal roof. |
THESSALONIKI DEPOSITS AND LOANS FUND | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | THESSALONIKI DEPOSITS AND LOANS FUND | |
Project Location | Greece - Thessaloniki | |
Construction Period | 1993 – 1995 | |
(%) Company Participation | 100 % | |
Renovation and reformation of the building of a branch of DEPOSITS AND LOANS FUND in Thessaloniki, Greece. |
CONSTRUCTION OF A COMPLEX SELLING TECHNICAL AND HOME EQUIPMENT (PRAKTIKER) IN LARISSA | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | EMPORIKI & KTIMATIKI LARISSAS S.Α | |
Project Location | Greece - Larissa | |
Construction Period | 1994 – 1995 | |
(%) Company Participation | 100 % | |
Construction of a shop selling technical and home equipment at a ground-level indoor area of 11.000 m2 and an outdoor area of 1.500 m2 all networks, parking area and surrounding area configuration. |
SHELTERS AND FACILITIES OF AIR COMMAND IN SKYROS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Air Force / Ministry of Defence | |
Project Location | Greece - Island of Skyros | |
Construction Period | 1993 – 1995 | |
(%) Company Participation | 60 % | |
Construction of third generation, special technology shelters for aircrafts and construction of operational facilities buildings. |
AT-GRADE INTERSECTION OF ACHARNON AVENUE WITH ATHENS-LAMIA NATIONAL HIGHWAY | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Acharnai, Prefecture of Attica | |
Construction Period | 1994 – 1995 | |
(%) Company Participation | 100 % | |
Construction of an at-grade intersection with all related road construction works and construction of a bridge at a curve of 160m with 5 openings (2x26,00 m + 3x36,00 m) with the Freco pre-stress system. |
CONSTRUCTION OF SECTIONS OF ATHENS - KATERINI MOTORWAY. SECTION 3, SCHIMATARI - RITSONA JUNCTION AND THIVON JUNCTION - YLIKI | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Thiva | |
Construction Period | 1991 – 1995 | |
(%) Company Participation | 100 % | |
Construction of motorway with all related works (secondary roads, intersections, service roads, road pavement, asphalt works, signage - protection, sewage, drainage, etc). |
SUPPLY, TRANSPORTATION AND INSTALLATION OF 100 PRE-FABRICATED RESIDENCES (CONTAINER-TYPE) READY FOR USE. PREFECTURES OF GREVENA AND KOZANI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefectures of Grevena and Kozani | |
Construction Period | 1995 – 1995 | |
(%) Company Participation | 100 % | |
SUPPLY, TRANSPORTATION AND INSTALLATION OF 100 PRE-FABRICATED RESIDENCES (CONTAINER-TYPE) READY FOR USE FOR THE TEMPORARY HOUSING OF EARTHQUAKE-STRIKEN AREAS IN THE PREFECTURES OF GREVENA AND KOZANI. |
SUPPLY, TRANSPORTATION AND INSTALLATION OF 100 PRE-FABRICATED RESIDENCES (CONTAINER-TYPE) READY FOR USE. PREFECTURE OF ACHAE | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefectures of Achae | |
Construction Period | 1995 – 1995 | |
(%) Company Participation | 100 % | |
Supply, transportation and installation of 100 pre-fabricated residences (CONTAINER-TYPE) ready for use for the temporary housing of earthquaka-striken areas in the prefectures of Achae |
DESIGN AND BUILDING OF INFRASTRUCTURE WORKS IN THE TEMPRORARY HOUSING AREA OF EARTHQUAKE VICTIMS IN AIGIO | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Aigio | |
Construction Period | 1995 – 1995 | |
(%) Company Participation | 100 % | |
Drawing up of the final project study, configuration of the ground where housings will be installed, construction of water supply and sewage networks, construction of concrete bases for the installation of the housings, connections with the networks of water supply, sewage and PPC and configuration of the access roads. |
SUPPLY, TRANSPORTATION AND INSTALLATION OF 50 READY FOR USE PRE-FABRICATED HOUSINGS OF 30 M2 | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefectures of Grevena and Kozani | |
Construction Period | 1995 – 1995 | |
(%) Company Participation | 100 % | |
Supply, transportation and installation of 50 ready for use pre-fabricated housings of 30 m2, ready for use for the temporary housing of earthquake-striken areas in the prefectures of grevena and kozani. |
INTAKE OF IRRIGATION NETWORK KARPEROU - DIMITRAS IN GREVENA PREFECTURE | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Ministry of Agriculture | |
Project Location | Greece - Prefecture of Grevena | |
Construction Period | 1992 – 1995 | |
(%) Company Participation | 100 % | |
Construction of an intake dam in Aliakmonas river. The project includes construction of a canal 5 m wide for the purification of incoming material, the construction of the pump station, the installation of delivery pipe F1000, 4.060 m long, as well as the installation of a canal for the water transportation to the re-calibration tank of irrigation networks. |
STEEL DISTRIBUTION NETWORK OF 19 BAR IN THRIASIO PEDIO | ||
![]() |
Project Categories | INDUSTRIAL & ELECTROMECHANICAL WORKS
|
Project Owner | Greek Public Gas Corporation, DEPA | |
Project Location | Greece - Aspropyrgos - Thriasio Pedio | |
Construction Period | 1994 – 1995 | |
(%) Company Participation | 100 % | |
Installation of a steel network with a total length of 27 km approximately, which consists of 8km of F8'' pipes, 17km of F6'' pipes and 2 km of F4'' pipes. The network begins at Aspropyrgos refinery, crosses Aspropyrgo and Elefsina and ends up at Mandra. |
BUILDINGS OF OPERATIONAL FACILITIES OF THE AIR COMMAND IN SKYROS | ||
![]() |
Project Categories | BUILDINGS
Airport Buildings |
Project Owner | Hellenic Air Force / Ministry of Defence | |
Project Location | Greece - Island of Skyros | |
Construction Period | 1993 – 1995 | |
(%) Company Participation | 76 % | |
Construction of special buildings of operational facilities of the Air Command along with service installations and constructions. |
DEPARTMENT OF VETERINARY MEDICINE - ARISTOTLE UNIVERSITY OF THESSALONIKI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | ARISTOTLE UNIVERSITY OF THESSALONIKI | |
Project Location | Greece - Thessaloniki | |
Construction Period | 1993 – 1995 | |
(%) Company Participation | 40 % | |
Construction of special buildings of operational facilities of the Air Command along with service installations and constructions. |
COMPLETION WORKS OF ITEA DETOUR AND ELECTRIC LIGHTING OF ITS JUNCTIONS | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Itea, Prefecture of Amfissa | |
Construction Period | 1994 – 1995 | |
(%) Company Participation | 100 % | |
Construction of earthworks, technical works, road pavement and asphalt works, as well as construction and electric lighting of the junctions, for the completion of Itea detour. |
ATHENS - CORINTHOS HIGHWAY ( Kakia Skala Section ) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Megara - Kakia Skala | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Construction of the MEGARA - KAKIA SKALA section of the ATHENS - CORINTHOS highway (km 43+600 to km 47+000). |
EVZONOI - ATHENS ROAD NETWORK. Makrygialos - Katerini Section (km 54+365 to km 59+000) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Makrygialos - Katerini | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Construction of the Makrygialos - Katerini section of the Efzonoi - Athens highway (km 54+365 to km 59+000). |
EVZONOI - ATHENS ROAD NETWORK. Makrygialos - Katerini Section (km 59+000 to km 63+500) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Makrygialos - Katerini | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Construction of a section of the Efzonoi-Athens highway section Makrygialos - Katerini from km 59+000 to km 63+500. |
NEMEA - TRIPOLI HIGHWAY. Velanidia - Artemisio Section | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Velanidia - Artemisio | |
Construction Period | 1985 – 1994 | |
(%) Company Participation | 98,5 % | |
Construction of the Velanidia - Artemisio section of Nemea - Tripoli highway. |
ATHENS - CORINTHOS HIGHWAY. Kineta - Ag. Theodoroi Section | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Kineta | |
Construction Period | 1991 – 1994 | |
(%) Company Participation | 49,5 % | |
Construction of the Kineta - Ag. Theodoroi section (58+511 to 62+026) of ATHENS - CORINTHOS highway. |
CONSTRUCTION AND ELECTROMECHANICAL WORKS FOR THE COMPLETION OF THE ARCHEOLOGICAL MUSEUM OF MITILINI AND ITS SURROUNDINGS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | MINISTRY OF CULTURE | |
Project Location | Greece - Mitilini | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 50 % | |
Construction and Electromechanical Works for the Completion of the Archeological Museum of Mitilini and its surrounding area. |
BUILDING OF THE GENERAL CONFEDERATION OF WORKERS IN GREECE (G.S.E.E.) | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | G.S.E.E | |
Project Location | Greece - Athens | |
Construction Period | 1990 – 1994 | |
(%) Company Participation | 100 % | |
Reformation - renovation of the neoclassic building of GSEE (Patission Str. - Ainiados Str. Athens, Greece) with the addition of a new floor. |
RESEARCH INSTITUTE OF PATRAS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Hellenic Ministry of Industry Research and Tecnology | |
Project Location | Greece - Patra | |
Construction Period | 1991 – 1994 | |
(%) Company Participation | 33,33 % | |
Design and construction of a building for the research institute of chemical engineering and high temperature chemical processing in Patras. |
CONSTRUCTION OF SECTIONS OF ATHENS - KATERINI MOTORWAY. SECTION 2 MARKOPOULO JUNCTION - OINOFYTA JUNCTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Oinofyta | |
Construction Period | 1990 – 1994 | |
(%) Company Participation | 100 % | |
Construction of motorway with all related works (secondary roads, intersections, service roads, road pavement, asphalt works, signage - protection, sewage, drainage, etc).
|
CONSTRUCTION OF STORAGE AREA FOR IMPERIO S.A. | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | IMPERIO S.A | |
Project Location | Greece - km 43.00, Athens - Lamia Highway | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 100 % | |
Building of Imperio's storage area. |
WORKING HOUSINGS IN VOLOS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | O.S.C.E. | |
Project Location | Greece - Volos | |
Construction Period | 1991 – 1994 | |
(%) Company Participation | 100 % | |
178 residences in 2-floor and 3-floor buildings with road construction; all networks, communal areas and other works in the surrounding area. |
"PANTELAKI" BUILDING OF SOFTEX (PHASES A+B+C) | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | SOFTEX A.E. | |
Project Location | Greece - Elaionas, Attica | |
Construction Period | 1994 – 1994 | |
(%) Company Participation | 100 % | |
Restoration of the damages at the supporting structure of the building caused by fire, using GUNITE technology (shotcrete). |
SOCIAL SECURITY INSTITUTION (IKA) BRANCH IN OINOFYTA | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Social Insurance Institute | |
Project Location | Greece - Oinofyta | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Construction of the IKA building in OINOFYTA of a total area of 3.500 m2 and 3floors; all netwoeks and works of a 3.000 m2 - surrounding area. |
SEWERAGE OF THE CITY OF LARISSA - 12/91 DISTRICT CONTAINERS | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Larissa Water Supply and Sewerage Company (DEYAL) | |
Project Location | Greece - Larissa | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Sewerage System in districts of the city of Larissa. |
SEWAREGE OF THE CITY OF LARISSA 3/91, DISTRICT STORM WATER RUNOFF AND SEWAGE PIPES | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Larissa Water Supply and Sewerage Company (DEYAL) | |
Project Location | Greece - Larissa | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Sewerage System in districts of the city of Larissa. |
SEWAREGE OF THE CITY OF LARISSA 3/91, DISTRICT STORM WATER RUNOFF AND SEWAGE PIPES | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | Kissos | |
Project Location | Greece - KISSOS Built-up area at Hortiatis, Thessaloniki | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Public utility system construction, kerb construction - road pavement of Kissos built-up area roads at Hortiatis, Thessaloniki. |
INDOOR GYM OF E.A.K. SYROU | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | GENERAL SECRETARIAT OF SPORTS | |
Project Location | Greece - Island of Syros | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 100 % | |
Repair of cracks at the Gym of EAK Syrou. |
6th & 14th PRIMARY SCHOOLS BUILDING OF PERISTERI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | SCHOOL BUILDING ORGANIZATION | |
Project Location | Greece - Athens | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 100 % | |
Construction of four 2-floor buildings with a total area of 3.235 m2 all networks and surrounding area configuration works. |
ADDITIONAL WORKS. LABORATORY OF REINFORCED CONCRETE. NTUA | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | NATIONAL TECHNICAL UNIVERSITY OF ATHENS (NTUA) | |
Project Location | Greece - Athens | |
Construction Period | 1994 – 1994 | |
(%) Company Participation | 100 % | |
Additional construction works and electromechanical installations. |
BRANCH OF IONIKI BANK IN KALLITHEA | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | IONIKI BANK OF GREECE | |
Project Location | Greece - Athens | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 100 % | |
Construction of a 2-floor building with basement; all internal networks. |
67th PRIMARY SCHOOL OF ATHENS | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | SCHOOL BUILDING ORGANIZATION (OSK) | |
Project Location | Greece - Athens | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 90 % | |
Construction of a school building of 2 floors and a ground floor, covering a total area of 2.540 m2, along with networks and works of the surrounding area of 2.780 m2. |
EXPANSION OF THE LIBRARY OF ARISTOTLE UNIVERSITY OF THESSALONIKI | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | ARISTOTLE UNIVERSITY OF THESSALONIKI | |
Project Location | Greece - Thessaloniki | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 40 % | |
Construction of an expansion of the library at the basement so that the surrounding area remains inaltered. Design and Construction. |
REINFORCEMENT - RENOVATION OF THE LISTED BUILDING OF A BRANCH OF BANK OF CRETE | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | E.T.B.A. | |
Project Location | Greece - Irakleio - Crete | |
Construction Period | 1993 – 1994 | |
(%) Company Participation | 40 % | |
Restoration and arrangement of an old building for the housing of the Hellenic Industrial Development Bank (ETBA). The building is listed in terms of facet, while its internal is being totally re-constructed. |
BUILDINGS AND SPORTS FACILITIES OF TEFAA PHASE I (INDOOR SWIMMING POOL) | ||
![]() |
Project Categories | BUILDINGS
|
Project Owner | DEMOKRITOS UNIVERSITY OF THRACE | |
Project Location | Greece - Komotini | |
Construction Period | 1991 – 1994 | |
(%) Company Participation | 100 % | |
Construction of buildings and sports facilities of the Physical Education Science and Sports Department (TEFAA) of Demokritos University of Thrace. |
IMPROVEMENT OF IRRIGATION IN NEA KERDYLIA, SERRES | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Ministry of Agriculture | |
Project Location | Greece - Nea Kerdylia, Prefecture of Serres | |
Construction Period | 1992 – 1994 | |
(%) Company Participation | 100 % | |
Construction of a pumping-station which will be fed by Strymonas river through a canal of trapeoid cross-section, constuction of a pipe water-supply network, construction of tank, and electrical installations. |
IMPROVEMENT OF THE ROAD STENI - STROPONES - METOXI IN SOUTHERN EUBOEA | ||
![]() |
Project Category | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Prefecture of Euboea | |
Construction Period | 1989 – 1992 | |
(%) Company Participation | 100 % | |
The construction of Stropones detour (earthworks, technical works, asphalt works, etc) is part of this improvement project. |
NEMEA - TRIPOLI MOTORWAY. SECTION: ARTEMISIO TUNNEL EXIT (KM 0+00) - TRIPOLI (KM 18+340) | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Artemisio - Tripoli | |
Construction Period | 1986 – 1992 | |
(%) Company Participation | 14,25 % | |
Construction of a motorway section from the exit of Artemisio tunnel to Tripoli. Project including at-grade crossings, junctions, irrigation networks, electric lighting and telephone connections. |
CONSTRUCTION OF SECTIONS OF ATHENS - KATERINI MOTORWAY. SECTION 1 OINOFYTA JUNCTION - SCHIMATARI JUNCTION | ||
![]() |
Project Categories | INFRASTRUCTURE
|
Project Owner | Hellenic Ministry for the Environment, Physical Planning and Public Works | |
Project Location | Greece - Oinofyta - Schimatari | |
Construction Period | 1985 – 1992 | |
(%) Company Participation | 100 % | |
Contsruction of earthworks, technical works, road pavement, asphalt works, signage for the improvement of Athens - Schimatari motorway from Oinofyta junction to Schimatari junction. |